How long does it take to get a building permit in Israel?

For straightforward projects that comply with the applicable zoning plan, the process typically takes between two and six months from submission to approval. If your project requires a variance or a new outline plan amendment, a public objection period must run, and the process can take one to three years or longer. Delays at the local planning committee are common, especially in large cities. Building in a buffer time of six months for most residential renovations is prudent.