Corporate Law

Does war excuse a company from performing a contract under Israeli law?

Rarely. Israeli law has no general force majeure doctrine, and the statutory excuse is frustration under Section 18 of the Contracts (Remedies for Breach of Contract) Law 5731-1970. It applies only where the party in breach did not and could not have foreseen the circumstances when contracting, could not prevent them, and performance became impossible or fundamentally different from what was agreed. Israeli courts have generally treated hostilities as a foreseeable risk of doing business in Israel, so war alone seldom meets that test.

Frustration (sikul) does not make the breach lawful or automatically end the contract. Under Section 18(a), a breach caused by frustrating circumstances simply cannot ground a claim for enforcement or damages. Section 18(b) then gives the court discretion to order restitution of what each party received and to allocate reasonable expenses spent on performance. Courts apply the test narrowly. Rising costs, currency swings and staff shortages caused by reserve-duty call-ups are unlikely to qualify on their own, while a specific government order that directly blocks the precise performance, such as the closure of the relevant site or port, stands a better chance.

Because Section 18 is so narrow, the contract usually decides the outcome. Israeli courts enforce a force majeure clause according to its wording, so a clause that names war, rocket fire, Home Front Command restrictions or the mobilization of key staff, and sets notice and suspension periods, protects far more than the statute. Foreign companies often assume that a force majeure doctrine applies by default, as it does in several civil-law systems. A party that simply stops performing risks cancellation of the contract and a damages claim, and prolonged silence toward the other side can breach the duty of good faith. Our guide to force majeure in Israeli contracts covers how such clauses are drafted.

⚖ In Practice
  • Governing law: Section 18, Contracts (Remedies for Breach of Contract) Law 5731-1970; Section 39, Contracts (General Part) Law 5733-1973
  • Competent authority: Magistrates' Court (Beit Mishpat HaShalom) for claims up to NIS 2.5 million and District Court (Beit Mishpat Mehozi) above that, unless the contract refers disputes to arbitration
  • Remedy where frustration is proved: no enforcement and no damages; restitution and reasonable expenses at the court's discretion
  • Fees/amounts: court fee on a monetary claim approximately 2.5% of the amount claimed, paid in two installments (2026)
  • Timeline: notice of cancellation must be given within a reasonable time after learning of the breach under Section 8 of the Remedies Law; the general limitation period is 7 years

From the full guide: Force Majeure in Israeli Commercial Contracts


Related Questions

Related Guides

Need legal help with this topic?
Get a Free Consultation with Adv. Eli ShimonyPrepared under the direction of Adv. Eli Shimony, Eli Shimony Law Office · Editorial policy

← Browse all Q&A